In order to construct a pipeline, staging areas and storage yards are cleared, strategically located along the planned right-of-way. They provide parking for construction equipment, employee trucks, and locations for office trailers.Both materials and equipments are transferred from our store to the worksite.
Category Archives: Staging
The survey crew also marks the center-line of the trench as a guide for digging. Road-cutter provides a clean edge through the material without transmitting cracks or damage further into the structure.Asphalt Pavement to be removed shall be neatly saw cut full depth along straight lines. Only such pavement shall be removed as is necessary..
The trench for the pipeline is dug after the ROW is cleared. The trenching crew moves in to dig the trench that holds the pipeline. The crew must create a trench deep enough to accommodate the pipeline, plus the required distance from the pipeline to the ground surface. Certain areas, such as waterways and road..
Pipes are laid above ground beside the trench, or within the trench on top of supportive sandbags in steep terrain. “Stringing” is the method by which pipeline construction workers assemble the pieces prior to completing the “puzzle,” making sure everything is accounted for. Every length of pipe is marked to indicate where it belongs along..